Startup Rejects After Bottle Changeover: Separate the Conversion from the First Good Run

Mechanical changeover can be finished while the line is still making rejects or waiting for quality release. One total downtime figure hides whether the loss comes from format work, mismatched materials, trial running or an acceptance decision.

Start with the approved old-to-new format pair, identified change parts and signed recipe/material checks. Trace the first defective bottle through the connected machines. Record mechanical completion, first conforming sample and quality release as different milestones.

Representative Allot Tech XGF monoblock used to discuss serial-specific bottle format interfaces
Catalog machinery, not a timed changeover test, a universal format kit or proof that every bottle size fits the same machine.

Use a changeover clock with clear endpoints

Define where the clock starts and ends: last approved old-format output, safe conversion, trial, first conforming new-format sample and quality release. Keep event timestamps and overlapping work. A machine's local conversion time and a line's released-output interruption are different measures.

Freeze both old and new bottle, neck, closure, label, message and pack revisions. Keep actual machine serials, recipes and part identifiers. A copied recipe name is not evidence that the intended physical format parts and approved materials were installed.

Illustrative non-overlapping ledger: 18 minutes of format work plus 12 minutes of trials plus 15 minutes of quality hold equal 45 minutes. These are planning values, not Allot Tech performance. Concurrent tasks must not be added twice, and waiting time should not be hidden inside a faster mechanical-change claim.

Find the first old/new-format mismatch

Keep startup, stable and restart samples separately. Identify where the first defect becomes visible before later rejects or alarms propagate across the line.

PatternEvidenceReview boundary
New bottle contacts one retained guide or pocketOld/new drawings, installed part IDs and safe observationsSerial-specific format parts and handoff compatibility
Old caps, labels or codes appear in the new runMaterial clearance, approved lots and job-change recordsOld/new material and data separation, not speed alone
Individual machines pass but connected startup failsLinked first-bottle samples, sequence and transfer stateConnected readiness and interface responsibility
Mechanics complete but released output remains delayedTrial results, hold reason, decision owner and timestampsAcceptance and quality hold separated from conversion work

Retest the defined format pair

This is not a live changeover or PLC-programming guide. Qualified personnel must follow isolation, guarding, cleaning and OEM procedures. Do not adjust moving guides, disable rejects or skip quality release to improve a stopwatch result.

  1. 01

    Preserve the old/new approved revision set, original recipes, format-part list and baseline event log.

  2. 02

    Use the site's clearance and verification procedure to confirm materials, messages and installed parts; record unknowns instead of assuming equivalence.

  3. 03

    Have the responsible specialist approve one permitted correction at the first mismatched interface and document the retained components.

  4. 04

    Repeat the agreed conversion, startup, stable run and restart sequence using the same endpoint definitions and quality sampling.

  5. 05

    Review new-format output and old/new segregation with quality. If return conversion is required, test it separately rather than inferring it from one direction.

Buy a defined changeover scope

A wrong part or mixed material requires a different corrective scope from a coordinated-startup problem. A long quality hold is not proof that another change-part kit will shorten the interruption. Separate these evidence paths before requesting automation.

Ask Allot Tech for a written format-pair matrix: retained/changed parts, settings responsibility, material/data clearance, permitted cleaning, required tools, connected milestones and acceptance endpoints. No universal kit, guaranteed conversion time or unsupported bottle-range extension is implied.

  • Machine serials and old/new approved package revisions
  • Recipe/job versions and installed format-part identifiers
  • Material clearance, lots and code-message approvals
  • First-defect samples with linked machine checkpoints
  • Non-overlapping conversion/trial/hold timestamps
  • Required conversion directions and responsible acceptance owners

Questions buyers ask

Does a completed mechanical change mean the line is ready for saleable output?

No. Confirm materials, recipe/data, connected transfer, new-format quality and release. Keep mechanical completion, first conforming sample and release as separate records.

Can one successful size change prove all formats and the reverse change?

No. Qualify the required old-to-new pair and return direction using approved revisions. Other formats, part sets or connected conditions need their own evidence.