Accept Machinery Against the Written Scope, Not Its Appearance

A factory acceptance test should state what is available to test, which project materials will be used, what evidence is recorded and which conditions remain for the installation site. The protocol must trace back to the approved contract and technical documents.

Solve the production problem before buying more machinery

Use a measured symptom and a controlled retest to decide whether the next action is material correction, maintenance, interface work or a machine change.

Uneven fill levels or suspected underfill?

Define height, net mass or volume as the agreed result. Compare valve groups, bottle lots and startup phases before changing the filler or inspection threshold.

Uneven fill levels and underfill

DIRECT ANSWER

What the buyer should decide

FAT is not an automatic guarantee of site output. It is a controlled opportunity to verify identity, workmanship, functions, project samples, alarms, documents, spares and open items within the agreed factory-test conditions.

Decision fieldConfirmWhy it changes the purchase
Before FATApproved scope, drawings, protocol and samplesCreates the acceptance basis
During FATSafety, dry/wet functions, interfaces and recordsTests observable requirements
After FATOpen items, evidence, spares, preservation and releasePrevents unresolved issues from disappearing

BUYER DECISION WORKBENCH

Agree the counting boundary before the machine runs

A FAT video is supporting evidence, not a complete acceptance record. Define the bottle and pack revision, materials, test conditions, observation window, count location and disposition of rejected or held units. A successful machine FAT does not establish final connected-site performance.

Protocol fieldAgree before testingRetain after testing
Identity and configurationSerial number, parts, recipes and approved drawingsAs-tested revision list and departures
Time and outputStart/end, count point, units and planned exclusionsCounter readings, good units and separate rejects/holds
Stop handlingHow interruptions and restarts are loggedEvent log with reasons and responsible reviewer
Format coverageFormats demonstrated and changeover checksEvidence for each tested format; untested items open
Acceptance decisionProject-specific criteria and authorized witnessesPass, conditional acceptance or re-test with assigned actions

Illustrative calculation only: 4,800 accepted bottles observed over 60 minutes equals 4,800 accepted bottles per hour for that test window. It is not a machine capacity claim. If counts are packs, record bottles per pack before conversion.

REQUIRED INPUTS

Prepare the evidence before selection

Missing fields should remain marked as open rather than converted into assumptions.

  • Signed technical scope
  • Approved drawings and BOM references
  • Project bottles/caps/labels/pack materials
  • Test utility and product limits
  • Acceptance criteria
  • Document and spare-part lists

TRADE-OFFS

Make the choice visible

Every option changes the machinery, operating work or project boundary.

Full-line FAT

Provides more interface evidence but may be limited by space, utilities and supplier scope.

Machine FAT

Confirms machine functions while leaving more site integration open.

Remote evidence

Can support review but does not equal an independent physical inspection.

PURCHASING RISKS

Do not let these gaps hide in the quotation

Carry every unresolved item into clarification and contract documents.

  • Arriving without approved criteria
  • Testing substitute materials without documenting limits
  • Ignoring alarms and recovery
  • Shipping with no controlled open-item list

WORK SEQUENCE

Move from data to a controlled next action

  1. 01

    Freeze the protocol.

  2. 02

    Confirm test materials and utilities.

  3. 03

    Verify identity and documents.

  4. 04

    Run safety, dry and wet checks.

  5. 05

    Record results and open items.

  6. 06

    Release only under the agreed process.

CONFIRMATION REQUIRED

Technical descriptions are selection guidance. Final machine, capacity, material, component, interface, utility and service details must be confirmed in the project proposal.

Content reviewed:

NEXT PURCHASING ACTION

Prepare the acceptance record before the visit.

Use the checklist as a project-specific starting point, then attach contract criteria.